SRINAGAR,
JUNE 29: According to the Power Controller Srinagar, to carry out
routine and preventive maintenance works including repair and branch cutting,
shutdown of 140 MVA, 132/33 KV grid stations Rawalpora shall be taken
on June 30, 2018, shutdown of Pampore-Rawalpora Circuit Ist on July
02-03, Bemina-Rawalpora Circuit 2nd on July 05,
Bemina-Rawalpora Circuit Ist on July 07 and Pampore-Rawalpora Circuit
Ist on July 08, 2018 from 9 am to 6 pm.
Besides, the
shutdown of Wanganpora-Safakadal 33 KV line shall be taken on June 30,
2018, from 10 am to 3 pm and shutdown of receiving stations Fateh
Kadal and Khanyar shall also be taken on July 02, 2018 from 10 am to 4 pm.
The power supply to the areas fed by these receiving/grid stations shall
remain affected on the said date and time.